Concurrent Delays in Construction

What Are Concurrent Delays in Construction?

Concurrent delays happen when two or more delays overlap and affect a construction project. These delays can come from the contractor, the owner, or even outside events like bad weather.

Types of Delays

Owner-Caused Delays

  • Late approvals.
  • Delayed access to the site. Typically permits. 

Contractor-Caused Delays

  • Poor planning. 
  • Not enough workers or equipment.

External Delays

  • Bad weather.
  • Labor strikes.

Example of a Concurrent Delay

Imagine a project to build in an office building in Ontario, 

  • Owner Delay- The owner is two weeks late approving building permits.
  • Contractor Delay- The contractor isn’t ready to mobilize on site due to subcontractor contract issues, causing a three-week delay.
  • External Delay- A winter storm shuts down work for one week.

How to Spot Concurrent Delays

Overlap in Timing

Delays must happen at the same time.

Critical Path Impact

Independent Causes

Delays need different reasons. For example, one delay could be from the owner, another from the contractor.

Project Completion Impact

Both delays must push back the final completion date.

How to Handle Concurrent Delays

Understand the Delays

Know if they’re caused by the owner, contractor, or external events.

Check the Contract

  • Does it allow for extensions of time (EOT)?
  • Does it explain cost reimbursement rules?
  • Are there clauses on how to deal with overlapping delays?

Notify Everyone

Send written notices about delays. Include:

  • What caused the delay.
  • How it’s affecting the schedule.

Analyze the Delays

Use scheduling tools to figure out what’s causing delays:

  • Critical Path Analysis- Find the tasks delaying the project.
  • Time Impact Analysis- Add the delays to the schedule and see the effect.

Split Responsibility

  • Owner-Caused Delays- The contractor might get more time and costs reimbursed.
  • Contractor-Caused Delays- No time extension or reimbursement.
  • External Delays- The contractor might get more time but usually no reimbursement.

Legal Context in Canada- CCDC 2 Example

Excerpt from CCDC 2 – 2020, used for educational purposes. Copyright Canadian Construction Documents Committee.

  • Owner Delays- Contractors get extra time and may be reimbursed for costs.
  • External Delays- Contractors get more time but no reimbursement unless linked to the owner.
  • Contractor Delays- No extra time or cost reimbursement.

Quick Recap

  • Concurrent delays overlap and affect the project’s finish date.
  • Use your contract to figure out what’s fair.
  • Analyze the delays to split responsibility fairly.
  • Communicate and document everything to avoid disputes.

Download Your Free PDF: Concurrent Delays in Construction